Plans the path from 'infra shipped' to 'full coverage with correct behaviours'. Five new plan docs in nestsClient/plans/: 1. 2026-05-07-t16-closure-roadmap.md — index + priority order. Three sequential steps + one independent track. 2. 2026-05-07-moq-relay-routing-investigation.md (Priority 1) — root-cause the moq-relay 0.10.x per-broadcast subscribe- routing race. Step-by-step: capture relay-side trace, write minimum reproducer, file upstream OR bump moq-relay version. Smoking gun + hypotheses already in place from the late-join-flake investigation; this plan turns that into actionable next steps. 3. 2026-05-07-tighten-cross-stack-assertions.md (Priority 2) — once the routing race is closed, replace the five soft- pass scenarios in BrowserInteropTest with hard floors. Lists each scenario, its current soft-pass behavior, and the proposed hard threshold. 4. 2026-05-07-cross-stack-interop-ci-gating.md (Priority 3) — re-add the hang-interop + browser-interop GitHub Actions jobs that were dropped in6829ab727/b94737de7. Includes the exact YAML to restore and a 10/10 sweep stability bar before merge. 5. 2026-05-07-framespergroup-production-rerun.md (independent track) — re-run the HCgOY two-phone field tests against current nostrnests production at multiple framesPerGroup values to settle whether the test pin (5) and production default (50) can converge. Estimated total: 2.5-3.5 days of focused work to fully close T16. After these four: I7 post-reconnect cliff and I12 GOAWAY remain open as genuinely upstream-territory items, tracked in their existing investigation docs.
133 lines
5.1 KiB
Markdown
133 lines
5.1 KiB
Markdown
# Plan: re-run HCgOY field tests against current production
|
|
|
|
**Status:** specced — pickup ready (needs prod-rig access).
|
|
**Cross-ref:** `nestsClient/plans/2026-05-07-framespergroup-reconciliation.md`
|
|
documents the conflict between the cliff plan's value (5) and
|
|
HCgOY's value (50). This plan settles which is current truth.
|
|
|
|
## What we're trying to settle
|
|
|
|
Production currently runs `NestMoqLiteBroadcaster.DEFAULT_FRAMES_PER_GROUP = 50`
|
|
based on HCgOY two-phone field tests at commit `6e4df4a`
|
|
(2026-05-05) which observed:
|
|
|
|
| `framesPerGroup` | streams/sec @ 50 fps | observed cliff window |
|
|
|---|---|---|
|
|
| 1 | 50 | ~3 s |
|
|
| 5 | 10 | ~13 s |
|
|
| 10 | 5 | ~16 s |
|
|
| 50 | 1 | not reached |
|
|
| 100 | 0.5 | never observed |
|
|
|
|
Interop tests pin `5` because the local `--auth-public ""` minimal
|
|
relay setup hits a *different* cliff (per-stream byte volume) at
|
|
`framesPerGroup = 50`.
|
|
|
|
The production deployment may have changed since 2026-05-05:
|
|
- nostrnests may have updated their `moq-relay` version
|
|
- their resource limits may have shifted
|
|
- the upstream `kixelated/moq` may have addressed one or both
|
|
cliffs
|
|
|
|
We don't know without re-running. **Cliff value at `framesPerGroup
|
|
= 5` may now be unbounded — if so, both rigs can converge on 5
|
|
and the test pin matches the prod default.**
|
|
|
|
## Test setup
|
|
|
|
### Rig A — interop env (already exists)
|
|
|
|
`./gradlew :nestsClient:jvmTest --tests HangInteropTest -DnestsHangInterop=true`
|
|
runs against local `moq-relay 0.10.25 --auth-public "" --tls-generate localhost`.
|
|
Long-broadcast scenario `long_broadcast_60s_tone_round_trips` is
|
|
the existing 60-second sustained-stream test pinned at
|
|
`framesPerGroup = 5`.
|
|
|
|
To probe other values, parameterize the helper:
|
|
|
|
```kotlin
|
|
// HangInteropTest.kt — runSpeakerToHangListen helper
|
|
private suspend fun runSpeakerToHangListen(
|
|
speakerSeconds: Int,
|
|
framesPerGroup: Int = 5, // ← new parameter
|
|
// ...existing params
|
|
): HangListenOutput { ... }
|
|
```
|
|
|
|
Then add scenarios `long_broadcast_60s_framesPerGroup_50` etc.
|
|
that pin different values. Expected outcomes today (per the
|
|
2026-05-01 cliff plan):
|
|
- `framesPerGroup = 5` — passes (current pin)
|
|
- `framesPerGroup = 10` — passes
|
|
- `framesPerGroup = 50` — fails (per-stream byte volume cliff
|
|
at the local minimal relay)
|
|
|
|
### Rig B — production deployment (needs maintainer access)
|
|
|
|
This is the gap. Rerunning the HCgOY two-phone field test pattern
|
|
needs:
|
|
- Two physical Android devices
|
|
- A nostrnests room (production endpoint
|
|
`wss://nostrnests.com/v0/ws` per `NestsConnect.kt`)
|
|
- The diagnostic-build of Amethyst that emits the cliff-detector
|
|
trace logs (see commit `6e4df4a`'s logcat run from 18:37:43..18:38:08)
|
|
|
|
The maintainer should run the same test pattern at:
|
|
- `framesPerGroup = 5` (current test value)
|
|
- `framesPerGroup = 10`
|
|
- `framesPerGroup = 25` (untested, midpoint)
|
|
- `framesPerGroup = 50` (current prod value)
|
|
- `framesPerGroup = 100` (full group; the cliff plan's
|
|
`fpg-all` reference)
|
|
|
|
For each, broadcast for 120 s and observe:
|
|
- Total streams forwarded by the relay
|
|
- Time-to-cliff if any (when the listener-side flow-control
|
|
snapshot stops incrementing `peerInitiatedUni`)
|
|
- Audio dropouts (perceptual + sample-count)
|
|
|
|
## Decision matrix after data lands
|
|
|
|
| Rig A passes at | Rig B passes at | Decision |
|
|
|---|---|---|
|
|
| 5, 10 | 5, 10, 25, 50, 100 | Keep prod 50; test pins 5 (current state) |
|
|
| 5, 10, 50 | 5, 10, 25, 50, 100 | Both rigs converge → unify on 50, test pin matches prod |
|
|
| 5, 10 | 50, 100 only (5 still cliffs) | Current state is correct; document permanently as "two cliffs in one binary" |
|
|
| 5 only | 50, 100 only (5 still cliffs) | The two cliffs are real; consider per-environment config |
|
|
| 5, 10, 50 | 50, 100 only (5 still cliffs) | Test rig fixed; production cliff still hits at 5. Test pin doesn't catch prod regression — bigger problem. |
|
|
|
|
The "decision" column drives the production-side change (or
|
|
non-change) to `DEFAULT_FRAMES_PER_GROUP`.
|
|
|
|
## What lands as code
|
|
|
|
After Rig B data is in:
|
|
|
|
1. Update kdoc on `NestMoqLiteBroadcaster.DEFAULT_FRAMES_PER_GROUP`
|
|
citing the new run's logcat dates / commit.
|
|
2. If the values converge, change the default to match. Update
|
|
the test-side `framesPerGroup = 5` pin to match the new
|
|
default — keep both rigs aligned.
|
|
3. If values still diverge, document it explicitly as a known
|
|
environment-dependent value. Consider exposing
|
|
`framesPerGroup` as a per-deployment config (currently only
|
|
exposed as a constructor parameter — wire to a config knob if
|
|
product wants per-deployment tuning).
|
|
4. Update `nestsClient/plans/2026-05-07-framespergroup-reconciliation.md`'s
|
|
"Recommendation" section with the data-driven outcome.
|
|
|
|
## Acceptance criteria
|
|
|
|
- A logcat dump from Rig B with `framesPerGroup = 5` for ≥ 60 s
|
|
showing whether the cliff still hits at ~13 s.
|
|
- Decision logged in the framesPerGroup reconciliation doc.
|
|
- If a value change lands, the test-side pin and production
|
|
default agree.
|
|
|
|
## Out of scope
|
|
|
|
- The local interop env's per-stream byte cliff at
|
|
`framesPerGroup = 50`. That's a separate thread; addressing it
|
|
would require either a different relay configuration or
|
|
patching moq-relay itself.
|