Plans the path from 'infra shipped' to 'full coverage with correct behaviours'. Five new plan docs in nestsClient/plans/: 1. 2026-05-07-t16-closure-roadmap.md — index + priority order. Three sequential steps + one independent track. 2. 2026-05-07-moq-relay-routing-investigation.md (Priority 1) — root-cause the moq-relay 0.10.x per-broadcast subscribe- routing race. Step-by-step: capture relay-side trace, write minimum reproducer, file upstream OR bump moq-relay version. Smoking gun + hypotheses already in place from the late-join-flake investigation; this plan turns that into actionable next steps. 3. 2026-05-07-tighten-cross-stack-assertions.md (Priority 2) — once the routing race is closed, replace the five soft- pass scenarios in BrowserInteropTest with hard floors. Lists each scenario, its current soft-pass behavior, and the proposed hard threshold. 4. 2026-05-07-cross-stack-interop-ci-gating.md (Priority 3) — re-add the hang-interop + browser-interop GitHub Actions jobs that were dropped in6829ab727/b94737de7. Includes the exact YAML to restore and a 10/10 sweep stability bar before merge. 5. 2026-05-07-framespergroup-production-rerun.md (independent track) — re-run the HCgOY two-phone field tests against current nostrnests production at multiple framesPerGroup values to settle whether the test pin (5) and production default (50) can converge. Estimated total: 2.5-3.5 days of focused work to fully close T16. After these four: I7 post-reconnect cliff and I12 GOAWAY remain open as genuinely upstream-territory items, tracked in their existing investigation docs.
4.8 KiB
T16 closure roadmap — full coverage with correct behaviours
Goal state. Every spec'd cross-stack scenario green in suite-mode sweeps, asserting its full design intent (no soft-passes, no vacuous threshold loosening), with CI gating live and stable.
Where we are. The merged claude/cross-stack-interop-test-XAbYB
branch ships 22 of 23 spec'd scenarios; each passes individually.
Suite-mode runs hit a residual moq-relay 0.10.x routing race on a
specific subset (~40-60% flake rate). Five scenarios soft-pass the
listener side as a known-flake mitigation. CI is intentionally
unwired pending stability.
This roadmap takes the suite from "passes individually" to "passes in suite + CI" through three sequential plans. None should be parallelized — each unblocks the next.
Priority 1 — 2026-05-07-moq-relay-routing-investigation.md
Why first. The race is the root cause of every soft-pass and the reason CI isn't wired. Without resolving it, downstream plans mask flake rather than catch regressions.
What lands.
- Either an upstream moq-relay version bump that closes the bug, OR a documented relay configuration tweak that does.
- Or, if neither: a filed
kixelated/moqissue with reproducer + trace pair, plus a documented decision to keep CI unwired until upstream resolves.
Acceptance bar. 5/5 sweep BUILD SUCCESSFUL on the existing HangInteropTest + BrowserInteropTest with their CURRENT soft-pass assertions intact. (The next step tightens those.)
Priority 2 — 2026-05-07-tighten-cross-stack-assertions.md
Why second. Once the suite is stable, every soft-pass that returned vacuous-pass on listener-side 0-frame outcomes is now HIDING regressions instead of side-stepping flakes. Replace each with a hard floor.
What lands.
- Five BrowserInteropTest scenarios get hard sample-count + FFT floors (or tightened existing ones).
- Gap matrix updated to reflect hard-pass coverage.
Acceptance bar. 5/5 sweep AGAIN, this time with hard assertions. If anything fail-flakes, the routing investigation isn't really done — loop back.
Priority 3 — 2026-05-07-cross-stack-interop-ci-gating.md
Why third. Stability + hard-asserts in place → CI is now a net positive (catches regressions, doesn't burn maintainer time on false reds).
What lands.
- Re-add
hang-interopjob (was at commit6829ab727's parent;git show 6829ab727 -- .github/workflows/build.ymlreverse gives the exact diff). - Re-add
browser-interopjob (same pattern, plus bun + Playwright caches). - Documentation update across the results plan + gap matrix.
Acceptance bar. 10/10 sweep before merge; ≥ 95% CI green rate over the first 2 weeks. If lower, the upstream race isn't fully closed — pull the jobs.
Independent track — 2026-05-07-framespergroup-production-rerun.md
This one doesn't block the closure roadmap. It can run any time after Priority 1 is done; it settles whether the test pin (5) and production default (50) can converge, or whether they must remain different. Either outcome is shippable.
What lands.
- Logcat data from a fresh two-phone field test against current
nostrnests production at multiple
framesPerGroupvalues. - A data-driven decision on whether to change the production default, the test pin, or neither.
Why it's parallelizable. Doesn't gate the test suite or CI;
it gates a one-line code change to NestMoqLiteBroadcaster's
default constant.
After all four close — what remains
Two open items, both genuinely upstream:
-
I7 post-reconnect listener cliff —
2026-05-07-i7-post-reconnect-cliff-investigation.md. The I7 reverse scenario passes its 2.5 s threshold but a regression test of "all post-reconnect data arrives" would require the moq-relay 0.10.x per-broadcast forward queue fix. Same upstream class as the routing race. -
I12 GOAWAY — only re-emerges if an IETF moq-transport target lands (currently moq-lite-03 only). Tracked in
2026-05-06-cross-stack-interop-test-results.md.
Beyond those: T16 reaches "full coverage with correct behaviours" when this roadmap closes.
Estimated wallclock
- Priority 1: 1–2 days (depends on whether upstream version bump fixes it, or we have to file + wait for upstream).
- Priority 2: 0.5 day (mechanical replacement of soft-passes with floors, plus rerun verification).
- Priority 3: 0.5 day (re-add CI jobs, run the 10× sweep, merge).
- Independent track (framesPerGroup): 0.5 day (needs prod-rig access).
Total: 2.5–3.5 days of focused work to take T16 from "infra shipped" to "fully closed".